Alstom TRAXX Vehicle Testing

Challenge

As Europe was imposing lockdowns in response to COVID-19 during March 2020, Ricardo’s testing team were in the Czech Republic conducting on-track testing for Alstom’s TRAXX MS3.

This electric-powered locomotive uniquely features an onboard 230kW ‘last-mile’ powerpack that enables travel on non-electrified track, a capability particularly valued in freight ports.

The tests were demonstrating the compatibility of the vehicle’s electrical systems with other trackside and onboard safety technologies.

The lockdown restrictions, however, threatened to impose significant delays on the client’s timetable.

Approach

Ricardo's team quickly developed a remote approach, with specially configured software, and cameras installed to stream live footage back to their homes in the Netherlands. A range of audio and visual issues had to be resolved to ensure secure and reliable access to the live data readings.

Results

Our experts were able to complete the test programme and collate sufficient data to compile the Intermediate Statement of Verification. This document was required to support authorisation for the nest stage of testing in The Netherlands.

It is estimated that we prevented a six-month delay in the vehicle’s progress towards authorisation.

Client

Alstom

Key Services

Testing and Authorisation

Location

Utrecht, The Netherlands

Contact our experts

Related projects

View all case studies
Shutterstock 2538883335

XL-Connect: Integrated bidirectional DC/DC converter and On-Board-Charger

Read article
Shutterstock 1380275897

Advanced Distributed Drive Software for Multi-Motor SUV Platform

Read article
Truck 2

Flexible Vehicle Control Supervisor for Hybrid and Electric Commercial Vehicles

Read article